HRSG Inspection Planning Guide
Inspection is part of routine maintenance for any Heat Recovery Steam Generator (HRSG). Visual inspections are performed at regular intervals in accordance with the requirements of regulatory bodies and insurers.
Misha Gadher, Mechanical and Thermal Process Engineer, and James Malloy, Senior Consultant, both of Tetra Engineering, have written on HRSG preservation for the October 2026 issue of Modern Power Systems. The article looks at one of the most neglected parts of HRSG operation: protecting the plant while it isn't running.
Owners face more uncertainty about when their units will be needed. Some plants have moved from baseload to cycling. Others sit on standby for long periods before being called back. Every idle period is a chance for corrosion to start.

Without proper layup, both the gas side and the water side are exposed. The damage can be severe:
Tetra recently assessed an HRSG that had been relocated and left without any preservation for several years. Advanced corrosion was evident, including on pressure parts.
Humidity is the key number for dry methods. Keeping relative humidity below 60% is essential, and getting it to 40% or lower greatly reduces the risk of corrosion.

The right choice depends on shutdown length, restart needs, equipment size and the resources on site. If a unit will be out for more than a week, long-term wet or dry layup should be considered, and planning should start before shutdown. Whatever the method, its effectiveness should be checked by monitoring humidity, nitrogen pressure or water chemistry throughout the outage.
In one recent case, Tetra developed a strategy for a large coastal combined cycle plant facing a six-month shutdown, where humidity and airborne chlorides raised the risk of corrosion. Each component got the method that suited it. The steam and gas turbines and the HRSG gas paths were dehumidified. The HRSG pressure parts were blanketed with nitrogen. The piping used nitrogen where it could be sealed, with passive drying or chemical protection elsewhere.
HRSG preservation during shutdowns: a key issue often neglected (Modern Power Systems, October 2026)
Tetra Engineering develops preservation strategies tailored to the expected shutdown length, equipment condition and site infrastructure. The one-day course Methods and Strategies for Effective Power Plant Preservation can also be run on site.
Stay up to date and refer to our large collection of technical white papers and articles


Inspection is part of routine maintenance for any Heat Recovery Steam Generator (HRSG). Visual inspections are performed at regular intervals in accordance with the requirements of regulatory bodies and insurers.


Tetra Engineering Group has extensive experience with HRSGs operating in potentially freezing environments. We’ve worked with plant owners from the North Slope of Alaska and Canada to Texas and Mexico where freeze damage and protection are important.


The latest updated edition of Tetra Engineering's HRSG Tube Failure Diagnostic Guide will be published August 15, 2016. Thousands of combined cycle professionals are familiar with Tetra's HRSG Tube Failure Diagnostic Guide; first published during the 'bubble' in construction in the early 2000s.